Week 2 Progress Report

Progress Report for Week 2 of Design of Cumene Production Facility

Team #: Mia Barrington, Jessica Blanding, Robert Duncanson

Goals for Week 1:

  1. Evaluate alternate separation sequences.

  2. Carry out flash and distillation column (shortcut and rigorous) simulations.
  3. Optimize process units and include recycle.

Summary of Accomplishments for Week 1:

  1. Team members decided on a final sequence of processes that would yield the correct amount of cumene
  2. After running simulation in ASPEN is was determined that a flash separator to separate the propylene first would not be cost effective because of the low level of separation that would be achieved. Therefore, It was determined to just use a single distillation column to separate the benzene from the cumene.
  3. Sensitivity analysis was run in ASPEN and the optimal process units were determined

Difficulties Encountered:

Aspen at times can be difficult to operate. Robert and Jessica spent an hours trying to get ASPEN to run the simulation. ASPEN had to be shut down and a new simulation started in order for the simulation to run.

CAPCOST is confusing. Jessica is having difficulty figuring out how to specify the equipment requirement in CAPCOST

Suggestion:

Extend the project a week and move the last test to final weeks to allow students to have more time to prepare a better report. Team Members expressed concern that the project is not feasible to complete in 3 weeks especially when the project description specifies that 4 weeks are necessary.

Team Activities in Week 12

Member (s) 

Task

Time spent (h)

Robert and Jessica

ASPEN simulation on reactor and sensitivity analysis

4

Mia, Robert and Jessica

Final PFD

4

Jessica

CAPCOST simulation

5

Mia, Robert

ASPEN simulation on distillation column and sensitivity analysis

6

Total (h)

19


 

Goals for Week 3:

  1. Finish Equipment Costing
  2. Finish final report
  3. Submit project

 

Project Timeline (listed tasks are for illustrative purpose only, modify and expand as necessary)

Task 

Week 1

Week 2

Week 3

Week 4

Preliminaries

 

Gross Profit and hand calculations of reactor sizing.

                            

Consideration of Alternatives

                            


Preliminary PFD

                            

Recommended Design

 

Base case simulation

                            

Sensitivity&Optimization

                            

Heat Integration

                            

Economic Analysis 

 

Equipment Sizing &Costing

                            

Profitability Analysis

                            

Monte Carlo Analysis

                            

Safety and Environmental 

 

Hazard Identification

                            

Waste Mitigation&Treatment

                            

Preparation of Written Report

                            


 