Wednesday, November 18, 2009

EPA Safety

Hazard Assessment and Procedures
The chemicals involved in this process are benzene, propylene, benzene and p-diisopropylbenzene. Although each chemical posed a hazard, benzene is the most hazardous. All chemicals should be utilized with safety in mind however; benzene must be handled with care. The health effects of benzene range from dizziness to cancer. Therefore, special precautions must be taken to ensure safety within the facility. In fact, in any workplace where benzene is used, stored or transported, workers must be aware of benzene’s properties, toxicity and safety procedures to meet the requirements of the OSHA Benzene Standard (29 CFR 1910.1028). Therefore, an annual training program will be implemented at the facility that ensures that all employees are knowledgeable of benzene policies and procedures. The OSHA Benzene Standard also provides permissible exposure limits for employees. In the event of an accidental release of benzene, the release must be reported to the appropriate authority, cleaned immediately while removing all sources of ignition. The storage and handling of feed chemicals has been responsible for some many explosions, including the Bhopal disaster in 1984. The plant accidently released methyl isocyanate gas into the environment. The accident stole the lives of 3,787 people. The effects of the gas leak are still seen today in Bhopal. The use of internal floating roof storage tanks are recommended for benzene bulk storage to ensure that the facility is safe from accidental releases and the tanks will be maintained according to state and local regulations.

First, source reduction was considered to reduce the amount of benzene released. Therefore, most of the benzene used in the process is recycled back into the process. The stream was then minimized and analyzed to determine if the direct release of benzene to the environment was a feasible option. Unfortunately, the risk was not in the allowable range therefore, waste treatment must be used. Gas adsorption was considered as a method of treating the recycle stream. However, the purge stream in conjunction with waste removal was more financially sound than utilizing carbon in a gas adsorber to remove the cumene in the recycle stream.

Production of cumene is a vital process for the use of phenol in industry. The recommended design of a cumene plant is to feed pure propylene and benzene to a reactor at molar flow rates of 102.3 and 105.6 kmol/h, respectively followed by two distillation columns. The yield of cumene produced is in accordance with the design specifications given. An economic analysis of the process yielded a net present value of $53.11 million after 12 years with only a 30% probability of failure.
The proposed process has been evaluated for environmental and safety hazards. It has been designed in accordance to all EPA standards and regulations with minimal release of toxic chemicals. This process is believed to be an economically and environmentally sound investment.

Huge Mistake!!!!!

While conducting the final economic analysis it was found that our total profit for the design process was -$22,000,0000. That is an extremely high number. We were floored with these results. After the culmination of our hard work to only make a negative profit hurt us deeply. We had to start back at the drawing board even after a few of team members were extremely frustrated that the deadline was quickly approaching.

Being the ever astute engineers that we are we figured out that it wasn't out utility cost that was killing our profit margins but the purchase costs for the raw materials. The specification of 2:1 or even 4:1 benzene ratio to propylene was found to be too high.

Economic Analysis

For this process it was determined that the COMd is $116.79 million. The fixed capital cost (FCIL) of process was found to be $3.97 million with a working capital of $9.69 million. The total cost of the raw materials (CRM), propylene and benzene, is $92.79 million. The process, which has benzene and di-isopropyl benzene as waste products, has a waste treatment cost (CWT) of $981,000. The total utilities cost (CUT) for the process was found to be $361,000. The total cost of labor (COL) was found to be $106,000. A total summary for the cost of manufacturing can be found in the file CAPCOSTanalysis.xlsx.

The revenue generated from the sale of cumene is $134.25 million dollars. Completing a cash flow analysis on the process shows the generation of a profit in year four of operation with a cash flow of $4.03 million. At the end of 12 years (2 years for construction and 10 years of operation) proposed plant would have a net present value (NPV) of $53.11 million. The discounted cash flow rate of return (DCFROR) is 63.11%. Based on the Monte Carlo Analysis of the NPV there is a 26% chance that the proposed process will not turn a profit. The median NPV is $39 million. Approximately 58% of the calculated values lie above the projected NPV for the process, $53.11 million. The summary for the Cash Flow and Monte Carlo analyses can also be found in CAPCOSTanalysis.xlsx.

Tuesday, November 17, 2009

Nearing the End

The project is almost done. Two more days to go. We are now doing the final optimization of the process and doing the final economic analysis of the process.

Over the weekend we had a minor setback. A team member received news that her grandmother passed and was understandably unable to work for two days, but the show must go on. The other two team members pressed forward with finalizing the final process. The final process was determined to feeding the pure benzene and propylene, mixed at a point in the stream (inter-stream mixing), to a heat exchanger. The mixture would then be fed to the reactor. The reactor effluent would be sent to a distillation column that would separate benzene to be recycled to the feed. The bottoms from that column would be fed to a second column where cumene would be separate for selling.

We are currently working on the economic cost evaluation and the environmental analysis of our process. Stay tuned for more updates for our senior design project


 

~JDB

Friday, November 13, 2009

Week 2 Progress Report

Progress Report for Week 2 of Design of Cumene Production Facility

Team #: Mia Barrington, Jessica Blanding, Robert Duncanson

Goals for Week 1:

  1. Evaluate alternate separation sequences.

  2. Carry out flash and distillation column (shortcut and rigorous) simulations.
  3. Optimize process units and include recycle.

Summary of Accomplishments for Week 1:

  1. Team members decided on a final sequence of processes that would yield the correct amount of cumene
  2. After running simulation in ASPEN is was determined that a flash separator to separate the propylene first would not be cost effective because of the low level of separation that would be achieved. Therefore, It was determined to just use a single distillation column to separate the benzene from the cumene.
  3. Sensitivity analysis was run in ASPEN and the optimal process units were determined

Difficulties Encountered:

Aspen at times can be difficult to operate. Robert and Jessica spent an hours trying to get ASPEN to run the simulation. ASPEN had to be shut down and a new simulation started in order for the simulation to run.

CAPCOST is confusing. Jessica is having difficulty figuring out how to specify the equipment requirement in CAPCOST

Suggestion:

Extend the project a week and move the last test to final weeks to allow students to have more time to prepare a better report. Team Members expressed concern that the project is not feasible to complete in 3 weeks especially when the project description specifies that 4 weeks are necessary.

Team Activities in Week 12

Member (s) 

Task

Time spent (h)

Robert and Jessica

ASPEN simulation on reactor and sensitivity analysis

4

Mia, Robert and Jessica

Final PFD

4

Jessica

CAPCOST simulation

5

Mia, Robert

ASPEN simulation on distillation column and sensitivity analysis

6

Total (h)

19


 

Goals for Week 3:

  1. Finish Equipment Costing
  2. Finish final report
  3. Submit project

 

Project Timeline (listed tasks are for illustrative purpose only, modify and expand as necessary)

Task 

Week 1

Week 2

Week 3

Week 4

Preliminaries

 

Gross Profit and hand calculations of reactor sizing.

                            

Consideration of Alternatives

                            


Preliminary PFD

                            

Recommended Design

 

Base case simulation

                            

Sensitivity&Optimization

                            

Heat Integration

                            

Economic Analysis 

 

Equipment Sizing &Costing

                            

Profitability Analysis

                            

Monte Carlo Analysis

                            

Safety and Environmental 

 

Hazard Identification

                            

Waste Mitigation&Treatment

                            

Preparation of Written Report

                            


 

Tuesday, November 10, 2009

Aspen Reactor

Aspen has been a tough program to crack. Following the tutorials turned out to be more work than we thought. We had to simulate the reactor kinetics of the cumene production using our hand calculations as a basis for our operating specifications. We used a mixer and a simple Rplug packed bed reactor model. We stuck with our 350 C temperature as well as the 35 bar pressure.

Aspen Plus overall seems to be a more intuitive program than chemcad but it still has its flaws. Setting up the reactor and specifying the components: propylene, benzene, cumene, and dissopropylbenzene. The SRK method was used as this was as suggestion that was read some where.

First run of aspen yielded nonsensical results. It showed that our propylene was comopletely reacted and we acheived 100% conversion. This was impossible due to all the text books drilling in our heads how achieving 100% conversion would need insane reactor volumes or specifications that aren't economically possible. This is generally why we assume conversions less than ideal (there is a reason why we call it ideal after all)generally around 98-60% at least. We realized quickly that our preexponential factors or reactor kinetics must be wrong. The little trick in Aspen is the need to specify the preexponential factor in SI units. Changing this and doing some basic SI conversion yielded acceptable results.

We then did a design specification to get the actual size of the reactor at 95% conversion. This was the key size of the reactor that everythign would be based on the 95% conversion.

We also ran a sensitivy analysis to determine the effects of pressure and temperature on reactor size. We also showed how temperature effects selectivity and how pressure had little to no effect on selectivity which makes sense.

There are the following results and we figured an optimal range of reactor size, temperature, and pressure that we would like to operate the reactor in order to get our correct design specifications.

P vs Volume 95% conversion

T vs Volume

Temperature Vs. Selectivity


From the graphs one could see how as the pressure increases the reactor volume decreases. However, there is a trade off between high pressure, reactor volume, and the cost of each. The optimal range seems to be between 25-45 bar for trying to keep the reactor volume around 30-10 cubic meters.

The T vs Volume chart highlights as well how the lower the temperature the greater the volume needs to be and there is associated cost between higher temperature and reactor volume. Since the selectivity increases with lower temperature chart 3. There is a need to balance both these variables to achieve the necessary design specifications.

These charts provided a calming feeling that we're at least on track with everything and just need to begin the next phase of our design. Our next step in our process would be to fire up a heat exchanger (excuse the pun) and a distillation column and do the same procedures with obtaining 99% product of cumene.


~RSD

Monday, November 9, 2009

Aspen Plus

Doing some preliminary chemical reactor simulations. It turns out doing the first trial simulation that the simulation returned no errors. However, it showed that all propylene reacted and there was literally 0.8ish kmol/hr of the undesired product formed. There might have been some miscalculations with converting the pre-exponential factor to the appropriate units for aspen.

Another idea is to actually employ a sensitivity analysis on the reactor plotting temperature vs. reactor volume and pressure vs reactor volume to see the result effects to get some type of idea of an ideal operating range/volume. There is a note that selectivity increases when temperature is lower but that will undoubtedly increase the size of the reactor. There seems to be some what of a balancing act and whatever we choose we have to justify such choices.

~RSD